Transport of transformer with weight of 216t

Transport of transformer from railway station Rudná u Prahy to power grid station VVN at Prague Řeporyje. The oversize load - transformator with height of 4,3m, lenght 12m and weight 216t was transported in special trailer THP 19 ( 19 axles)

Sep 16, 2013 10:08 AM More

We made it!! Demolition of three bridges on the highway D1

We carried out the demolition of three bridges on highway D1 in section 21, exit 153 Lhotka and exit 162 Velká Bíteš during works on the modernization of highway D1.

Jul 8, 2013 8:00 AM More

We made it!! Demolition of three bridges on the highway D1

We carried out the demolition of three bridges on highway D1 in section 21, exit 153 Lhotka and exit 162 Velká Bíteš during works on the modernization of highway D1.

Jul 8, 2013 8:00 AM More

Cooperation establishment with company Petr Březina – APB Plzeň

In the framework of the Project SGS, created by Mr. Jan Petrů and named Swept paths of oversize cargo design vehicle and issue solved in the Project „Young explorers“ the cooperation with company Petr Březina – APB Plzeň a.s. was established. This company is specializing in transport and in heavy and oversize cargo transportation.

Jun 15, 2013 3:08 PM More

Thanks for help during a flood

Thanks for help during a flood

Jun 14, 2013 2:38 PM More

Transit through hub Plzeň

We are executing an earthwork in Prokopova street and earthworks for the new subway in Šumavská street in Pilsen.

Apr 16, 2013 2:38 PM More

we transported a mill‘s casing about weight 144 tons to the Lovosice harbor

We transported a mill’s casing about weight 144 tons from Přerov to Lovosice. Oversized cargo of diameter 8,8 m were transported on special leader STZ THP 16 (no. of axis: 16).

Apr 11, 2013 3:08 PM More

Demolition of hall Lego Celestica in Kladno

We are currently working on the demolition of the factory hall Celestica Lego in Kladno. This is the complete demolition of the building include floors, energy block, fire tank and outbuildings.

Jan 25, 2013 2:38 PM More

we transported a mill‘s casing about weight 119 tons to the Mělník harbor

We transported a mill’s casing about weight 119 tons from Přerov to Mělník. Oversized cargo of diameter 8,48 m were transported on special leader STZ THP 14 (no. of axis: 14).

Aug 9, 2012 3:08 PM More

Transportation of the bus to London

Transportation of the bus by designer David Černý to London, venue of 15th Olympics. With using of the frame loader we transported unique double-decker bus from work-room of Prague designer before the Czech House in London.

Jul 25, 2012 3:08 PM More