2005 Construction of new building Prague

Construction of new office building was done by use of two cranes AC 100.

More information

2005 Unloading of tracks Pilsen

With use of telescopic crane we unloaded track lengths.

More information

2005 Assembly of bridge Telč (Vodňany)

With telescopic crane we mounted girders of bridge at Vodňany.

More information

2005 Installation and transport of tank Kopidlno

By crane AC 350 we have done a complete crane work including transport of the tank.

More information

2005 Engineering Blatná

Engineering Blatná – loading and transport of hopper. We did a complete crane work including transportation of  the hopper.

More information

2005 Assembly of line Chanovice

Assembly of line for wood processing we implemented by telescopic crane AC 50.

More information

2005 Hall Hořovice AC 30

We implemented complete crane work together with transport of technology at Hořovice.

More information

2005 Assembly of tower crane Prague Chodov

Tower crane at the Prague Chodov we assembler with use of crane AC 200.

More information

2005 Assembly of pillar casing for bridge Valík