References(Page 41)

References(Page 41)

References

2008 Sokolov – Hexion

In area of Hexion Sokolov company we realize a demolition works, earthworks and redevelopment works include sheeting of shinking shaft.

More information

2008 Nosovice - Hyundai

We realize a complete earthworks, nets, roads and walkways in Hyundai area about 200 hectare in Nosovice.

More information

2007 Cooling tower demolition in Beroun

Complete demolition of cooling tower in area Ceskomoravsky cement in Beroun include material disposal.

More information

2007 Bridge demilition in Stenovice

Bridge demolition in Stenovice were realized partly with using of crane technique and hereafter we demolished the pillars include its foundation.

More information

2007 Chestnut tree replant at center of Liberec

Whooping action was performed with help of our technique at the center of Liberec. We replanted  150 year old tree.

More information

2007 Installation of autoclave

Transport of autoclave and following assembly we perfofmed with use of truss crane TC 2800 and telescopic crane AC 100.

More information

2007 Stadium construction Slávie

Construction of new stadium Slávie was made by use of truss crane CC 2000 and telescopic crane AC 100.

More information

2007 Technology of Pilsen heating plant

Telescopic cranes AC 100 plus AC 350 installed technology at pilsen heating plant.

More information

2007 Assembly staircases

We realized assembly of staircases together with transportation.

More information